Council asked to spend $17.7 million on Oncor power vaults so convention center expansion work can start

An item added to Tuesday's City Council agenda would order long lead-time electrical equipment for four vault locations at the Kay Bailey Hutchison Convention Center, paid from the convention center's construction fund.

Lena Stroud· AI-assisted, edited by Jake Team

November 7, 20261 min read

Dallas city hall dome - illustration, Jake Team LLC

The Dallas City Council will be asked Tuesday, Nov. 10, to approve $17.7 million in agreements with Oncor Electric Delivery for electrical gear needed before the expansion of the Kay Bailey Hutchison Convention Center can move ahead.

The item was added to the council's agenda for individual consideration. It would authorize four discretionary service agreements with Oncor at the convention center's address, 701 S. Lamar St., each a pre-order for long lead-time equipment at a separate underground vault location. Each of the four carries a cap of $4,429,084.57, for a total of $17,716,338.28.

Why the city is paying

According to the proposed resolution, existing Oncor electrical infrastructure on the convention center property has to be decommissioned, relocated or newly established to serve the expanded facilities as construction begins on the master plan.

Because that equipment sits on convention center property rather than in a public right-of-way, the resolution says, the city needs the agreements so Oncor can order materials and remove existing equipment before construction.

The money would come from the Convention Center Capital Construction Fund, administered by the Department of Convention and Event Services.

Part of a larger plan

The work is tied to Component One of the convention center master plan, which the resolution says covers the building concept along with transportation, land use and funding. In November 2024 the council hired Trinity Alliance Ventures, a joint venture, as construction manager at risk for the first component: the expansion west of Lamar Street and related demolition.

The council meets at 9 a.m. Tuesday in the Council Chambers on the sixth floor of City Hall, 1500 Marilla St.

Sources

cityofdallas.legistar1.com

cityofdallas.legistar1.com

Share

Lena Stroud· AI-assisted, edited by Jake Team

Lena Stroud covers Dallas city hall, the council, and county government.

Related Stories

More in Texas