Downtown-to-Fair Park link stalled at a DART crossing would cost $2.2 million more to finish

Work on the CBD Fair Park Link stopped in March 2023 while DART required a new federal safety review at Elm Street. A change order on Tuesday's council agenda would lift the contract to $8.15 million and push completion to December 2027.

Wade Ramos· AI-assisted, edited by Jake Team

November 5, 20262 min read

Civic Infrastructure - illustration, Jake Team LLC

A walking and biking connection between downtown and Fair Park that has sat unfinished for more than three years at a DART rail crossing would cost about $2.2 million more to complete under a change order the Dallas City Council considers Tuesday.

The consent item would raise the city's contract with DDM Construction Corp. for the CBD Fair Park Link, from Hall Street to Main Street, by $2,214,096.23, to $8,152,001.10. It would also extend the contract by 240 days, to Dec. 31, 2027. Almost all of the added money, $2,202,897.23, would come from the DART Six-Year General Mobility Program Fund, with $11,199 from a water capital fund.

How the project stalled

The council awarded the original $5.84 million contract in September 2021, and construction began in March 2022, according to the agenda information sheet from the Department of Transportation and Public Works.

In June 2022, DART told the city that no work could happen inside the railroad crossing until a Preliminary Hazard Analysis was finished and approved under updated federal rail safety requirements. DART had approved the original plans in February 2018, but the new rules required more safety analysis and design changes.

Once everything outside DART's right-of-way was done, the city suspended construction on March 17, 2023.

DART issued a no-objection letter in May 2025 that allowed work in its right-of-way to resume. An administrative change order approved Oct. 7 added 1,510 days to the contract at no cost so the contractor could remobilize and order long-lead parts for the Elm Street crossing signal system.

Why the price went up

Staff wrote that inflation in material and labor costs during the long suspension means some remaining work can no longer be done at the original unit prices. Counting four earlier change orders, the contract would end up about 40% above the 2021 award.

Until the crossing is built and working, pedestrians and bicyclists cannot safely cross the DART tracks at Elm Street, leaving the corridor incomplete, the memo says. Staff described finishing it as necessary for a safe, ADA-compliant route in line with the city's Vision Zero goals. The project is in Council District 2.

The council meets at 9 a.m. Tuesday, Nov. 10.

Sources

cityofdallas.legistar1.com

webapi.legistar.com

cityofdallas.legistar1.com

Share

Wade Ramos· AI-assisted, edited by Jake Team

Wade Ramos writes about community life, schools, public safety, and local events in Dallas.

Related Stories

More in Texas