Dallas Water Utilities has awarded three construction contracts since the City Council let staff give price less weight when scoring bids for civil works, and all three came in under the engineers' cost estimates, according to a follow-up memo prepared for Wednesday's Transportation and Infrastructure Committee.
The three awards total about $176 million against estimates of roughly $225.6 million, a combined difference of about $49.6 million. In two of the three, the contract did not go to the lowest-priced proposer.
What changed
State law has required since September 2021 that price make up at least half of the scoring when a Texas local government picks a civil works contractor through competitive sealed proposals. The same statute lets a governing body drop that share to as low as 36.9% if it finds a lower weight is in the public interest.
The council made that finding on May 14, 2025, and delegated the decision on each project to department directors or their deputies so solicitations would not each need a separate council vote, the memo says.
For all of the water utility's projects since then, price counted for 40% of the score. The other 60% covered the contractor's approach to the work, its experience and qualifications, key personnel and use of small businesses under the city's DRIVE policy.
The three contracts
- Lake June Pump Station and Reservoir Replacement, Package A, awarded Sept. 24, 2025: $72.7 million against a $76.8 million estimate. The winner was the second-lowest of three proposals.
- Southwest Pipeline, Phase 1A, awarded Aug. 25, 2026: $89.9 million against a $130.8 million estimate, the largest gap. The winner was the second-lowest of four proposals.
- 60-Inch Wastewater Rehabilitation Project, awarded Sept. 9, 2026: $13.3 million against an $18 million estimate. The winner had the lower price of two proposals.