Police training center at UNT Dallas faces an $82 million hole after the safety bond's defeat, and the city is weighing options

A memo for Monday's Public Safety Committee says Dallas is working with its contractor and fundraisers on the funding gap. The bond would have supplied $82 million of the center's estimated $185 million cost.

Wade Ramos· AI-assisted, edited by Jake Team

November 8, 20262 min read

Civic funding - illustration, Jake Team LLC

Dallas is reworking the money plan for its new police training center at UNT Dallas after voters turned down the $443 million public safety bond that was supposed to finish paying for it.

A memo prepared for Monday's Public Safety Committee meeting says that, because of the Nov. 3 bond result, the city is "evaluating options with the contractor and the fundraisers to address the funding gap." Staff plan to bring those options to the committee and the full City Council "in the upcoming months," according to the memo from Chief of Public Safety Dominique Artis.

It gives no figures or dates beyond that.

What the bond was carrying

The center, planned for 7300 University Hills Blvd. on the UNT Dallas campus, has an estimated construction budget of $185 million, according to an Oct. 28 council item. The city's October update to the same committee listed $107 million committed so far:

  • $50 million from the 2024 bond program
  • $25 million in state grants, $10 million from 2023 and $15 million from 2025
  • $10 million from the Communities Foundation of Texas' W. W. Caruth Foundation Fund, of which $7.5 million had arrived
  • $10 million from QuikTrip
  • $12 million in other private pledges

That update said $82 million of the bond would have gone to finishing construction and "closing the funding gap." Private donors had committed $32 million toward a $70 million fundraising goal, and staff said the other $38 million was expected to come in on schedule.

Work already underway

Crews began clearing the site in September after a Sept. 3 groundbreaking, and the October memo put the site package at 5% complete. Construction is scheduled to wrap up in July 2028.

The Oct. 28 council item showed how the city had planned around the uncertainty: of contractor Swinerton Builders' $158.6 million price for the buildings phase, it set aside only the $20 million then on hand, with more to follow as money became available.

Proposition A failed with 56% of voters against it and 44% in favor, according to unofficial results reported by NBC 5. City Manager Kimberly Bizor Tolbert said in a statement to NBC 5 that "the voters have spoken, and we respect their decision," and that the city would keep working with council members and private and philanthropic partners "to identify solutions."

District 9 council member Paula Blackmon, who unsuccessfully pushed this summer to list each bond project separately on the ballot, told NBC 5 the result showed voters "don't have faith in their city government."

The October update also listed an informational community meeting on the training center from 5:30 to 7 p.m. Tuesday, Nov. 10, at Singing Hills Recreation Center. The committee meets at 1 p.m. Monday at City Hall.

Sources

dallascityhall.com

dallascityhall.com

webapi.legistar.com

NBC 5 Dallas-Fort Worth

Share

Wade Ramos· AI-assisted, edited by Jake Team

Wade Ramos writes about community life, schools, public safety, and local events in Dallas.